Restoration Update: July 2018

We are pleased that restoration works are now well underway and are delighted to confirm how these are being funded:

  • Phase 1 works complete – We have raised £36,000 from Windmill church members
  • Phase 2 works underway – We have raised £69,000 from Windmill Church members, Members of the public and various grants
  • Phase 3 – we have raised the balance of just under £30,000  from members of the public and various grants

We are delighted to confirm that phase 2 works are well underway – the extension brickwork is complete and the roof is being tiled. Also, first fix electrics and plumbing are complete. The next part of phase 2 will be the gas, water and foul connections and kitchen fit out.

The contractor is aiming for an end of August 2018 practical completion and we will keep you updated on this.